July 8, 2024 | By John A. Tirpak
The cost overrun on the Air Force’s LGM-35A Sentinel intercontinental ballistic missile is more than twice what was anticipated early this year—81 percent compared to 37 percent—but Pentagon acquisition and sustainment chief William LaPlante has certified that the program must continue, the Department of Defense announced July 8.
The Pentagon also indicated the program will be delayed at least three years, instead of the two previously predicted, and the Air Force alone seemingly must bear the cost of the overrun.
Quote:
While Sentinel is being restructured, “we’ll do what it takes to sustain Minuteman III to meet warfighter requirements,” Hunter said.